**Summary:** Major refocus toward concise, practical what-if scenario planning for project management. Support files and much theory removed. - Streamlined the skill to focus on deterministic what-if scenario analysis (WISA) for projects. - Removed extensive methodology descriptions and all external reference files. - Clearly structured step-by-step process for simulating project plan changes in schedule, resources, or costs. - Added specific guidance for using Excel, MS Project, and Primavera tools. - Provides a simple, consistent output and evaluation format for scenario impacts and recommendations. - Enforces baseline validation and limits complexity for practical real-world use.
安装命令 点击复制
技能文档
# What-if Scenario Planning (WISA)
When to Use
Use this skill when:- A project plan needs risk simulation before execution
- The user asks “what if this changes?” in a project context
- There is uncertainty in schedule, cost, or resources
- The user is working in Excel, MS Project, or similar tools
Core Objective
Simulate alternate project scenarios by modifying key variables (duration, resources, cost) and evaluate their impact on:- Project timeline
- Critical path
- Total cost
- Resource utilization
Execution Steps
Step 1: Establish Baseline Plan
Ensure a complete baseline exists:- Tasks with durations
- Dependencies (network/PERT)
- Resources assigned
- Cost estimates
Step 2: Identify Variables
Extract or ask for uncertain variables:- Resource availability
- Task duration variability
- Budget constraints
- External risks (delays, logistics, approvals)
Step 3: Define Scenario
Create a structured scenario: Format:- Scenario Name:
- Variable Change:
- Duration/Impact Change:
- Time Window (if applicable):
- Resource A unavailable for 3 days starting Day 10
Step 4: Modify Project Model
If Excel:- Adjust input cells (duration/resource %)
- Use:
- Duplicate baseline
- Modify:
Step 5: Simulate Impact
Recalculate project plan and capture:- New project duration
- Critical path changes
- Cost variation
- Delayed milestones
Step 6: Compare with Baseline
Create structured comparison: | Metric | Baseline | Scenario | |--------|----------|----------| | Duration | | | | Cost | | | | Critical Path | | |Step 7: Evaluate Acceptability
Decide:- Acceptable → proceed with scenario plan
- Not acceptable → propose mitigation:
Step 8: Recommend Action
Always provide:- Impact summary
- Decision recommendation
- Optional mitigation strategies
Output Format
Return results in this structure:Scenario Summary
- Scenario:
- Key Change:
Impact Analysis
- Duration Change:
- Cost Impact:
- Critical Path Impact:
Recommendation
- Decision:
- Suggested Actions:
Rules
- Do NOT simulate without a baseline
- Limit scenarios to avoid combinatorial explosion
- Prefer clarity over complexity
- Always quantify impact (time/cost)
- If data is missing → ask user before proceeding
Notes
- This is deterministic scenario analysis (WISA)
- For probabilistic analysis, suggest Monte Carlo simulation
- Best used during planning and scheduling phase
Validation
Before finalizing:- Ensure dependencies are preserved
- Check calculations consistency
- Validate assumptions with user context
- Confirm outputs are realistic (no negative durations, etc.)